Transmission and System
Operation Business Group
Transmission
and System Operation (TSO) business group is headed by the General Manager and
is responsible for design, construction, operation and maintenance of
transmission system of voltage level of 66 kV and above. Under this business
group, there are three departments, namely, Transmission Line/Substation
Construction Department, Grid Operation Department and System Operation
Department each headed by a Director.
In FY 2006/07, NEA and IL&FS Infrastructure Development Corporation Limited of
India (IL&FS) have concluded a deal according to which two joint venture
companies will be formed, one in Nepal and the other in India. In JVC-Nepal,
NEAwiII invest 50% equity while IL&FS will invest 26% equity. The remaining
shares will be offered to financial and other institutions. NEA will own equity
in JVC-lndia as well. The joint venture companies will be responsible for
project development, construction, operation and maintenance of the portion of
cross- border transmission system in respective countries. Four projects,
namely, Butwal—Gorakhpur, Duhabi—Purnea, Dhalkebar—Muzaffarpur and Anarmani—Siliguri
Cross Border Transmission Line Projects will be undertaken for development over
the time. Among these transmission lines, the first two will be developed in the
first phase within two years. Once built, these cross-border lines will
facilitate greater volume of power trading between Nepal and India.
Transmission Line I Substation Construction Department
Transmission Line/Substation Construction Department is responsible for the
construction of new transmission lines and substations of 66 kV and higher
voltage level. In this fiscal year, the Department has completed Birganj
Corridor 132 kV Transmission Line Project, which consists of 17 km long
Pathalaiya-Parwanipur double circuit transmission line and a 45 MVA, 132/11 kV
substation at Parwanipur. Completion of this project has relieved the
overloading of Hetauda-Birganj 66 kV transmission lines to some extent and has
enabled NEA to lift off-peak hour load shedding in the area. This Department is
also implementing two 220 kVtransmission lines, three 132 kVtransmission lines
and three reinforcement projects. A brief description of these projects are
given below.
Khimti-Dhalkebar 220 kV Transmission Line Project:
Khimti-Dhalkebar 220 kV Transmission Line will have the distinction of being
the first ever 220 kV transmission line in Nepal. Once completed this
transmission line will improve the reliability of power evacuation from Khimti-1
Hydroelectric Project (HEP), improve the voltage-drop problem in eastern Nepal
and provide a direct route for export of available power to India via Dhalkebar
Substation. This line will also serve the purpose of evacuation of powerfrom
planned UpperTamakosi Hydroelectric Project.
The Project comprises of a 75 km long 220 kV transmission line on double circuit
towers from Khimti-1 HEP to Dhalkebar Substation and 132 kV line bay extensions
at each end of the line. Single circuit duplex BISON conductor will be strung
and charged at 132 kV level till Upper Tamakoshi HEP is built.
Contracts have already been awarded for the 220 kV transmission line including
the 132 kV bay extensions. Fabrication of towers has already begun. Land
acquisition for transmission line will be initiated shortly. Environmental
Impact Assessment (EIA) and Social Impact Assessment (S IA) have been completed.
Power Grid Corporation of India Ltd. is providing the consulting services for
the Project. The estimated cost of the Project is US$ 22 million and is funded
jointly by GoN, NEA and IDA. The project is expected to be completed by 2008.
Hetauda-Bardaghat 220 kV Transmission Line Project:
INPS has major load centers at central and eastern Nepal, whereas, the
generating stations are located mainly in western and central region. The
present network shows that there is a weak link from Hetauda to Bardaghat. The
connection of Hetauda to Bardaghat is at 132 kV single circuit transmission line
with PANTHER conductor. A fault in either Marsyhayngdi-Siuchatar or in
Bharatpur-Hetauda Transmission Line section will overload HetaudaBardaghat
Transmission Line resulting into the collapse of the entire INPS system. The
existing Hetauda-Bardaghat transmission line will be further overloaded if the
generation capacity is increased to meet the unconstrained/normal system load.
With the introduction of Middle Marsyangdi HEP into the system, the situation
will be even more severe. Hence, upg radation of transmission capacity between
Hetauda and Bardaghat has been a task of priority for NEA. Keeping in view of
the above, NEA has decided to implement Hetauda-Bardaghat 220 kV Transmission
Line Project. The Project comprises of approximately 143 km long double circuit
220 kV transmission line connecting the existing Hetauda and Bardag hat
Substations using ACSR BISON duplex conductors. EIA study has been completed,
the report of which is under review by the concerned governmental agency. The
cost of this Project is estimated at US$ 39.2 million.
Thankot-Chapagaon-Bhaktapur 132 kV Transmission Line Project
Thankot-Chapagaon-Bhaktapur 132 kV Transmission Line Project comprises of nearly
28 km long 132 kV transmission line from Thankot (Matatirtha) to Bhaktapur via
Harisiddhi. This Project will complete the 132 kV ring-main system in Kathmandu
valley. The 132 kV ring main, on one hand, will greatly assist in catering the
increasing demand in the valley and on the other hand, will help to bring down
system loss, improve the quality and reliability of the power supply in the
Valley. About 26 km of this line will be double-circuit while the rest will be
four-circuit. The Project includes the construction of a new 132 kV switching
station at Matatirtha, a new 132/11 kV, 22.5 MVA substation at Harisiddhi and
upgrading of existing Bhaktapur and Balaju Substations. Estimated cost of the
Project is US$ 20 million. The Project is being financed by GoN, NEA, ADB and
OPEC. So far 40% of the line construction work has been completed. The design
works of substations are underway. The Project is planned to be completed by
2008.
Middle Marsyangdi—Dumre-DamauliMarsyangdi 132 Transmission Line Project:
Middle Marsyangdi—Dumre-Damauli-Marsyangdi 132 kV Transmission Line Project is
envisaged to improve security and reliability of the network and to facilitate
evacuation of power from the ongoing Middle Marsyangdi Hydroelectric Project (MMHEP).
This Project will also open up the way for power evacuation for future
hydroelectric projects in Marsyangdi basin. The Project component comprises of
stringing of second circuit from MMHEP to Dumre, construction of double circuit
transmission line from Dumre to Damauli and stringing of second circuit from
Dumre to existing Marsyandi HEP. Route alignment survey for the Dumre-Damauli
section of the transmission line has been completed and EIA study is underway.
This project is estimated to cost US$ 6.8 million.
Kabeli Corridor 132 KV Transmission Line Project:
Kabeli Corridor 132 Ky Transmission Line Project has been envisaged to
evacuate power from proposed 30 MW Kabeli-A HEP in Mechi zone of the country.
This line will also pave way for the development of other hydroelectric projects
in Kosi basin. Survey works for the route alignment of the transmission line is
currently in progress. EIA study will start from next fiscal year. This project
is expected to cost about US$ 18.4 million. The Project comprises of
construction of single circuit stringing in double circuit towers for the first
stage. Discussions are underway with the World Bank for funding this Project.
Chandranigahpur System Reinforcement Project:
Chandranigahpur System Reinforcement Project comprises of construction of
132/33/11 kV substation at Chandranigahpur and 74 km long 33 kV sub-transmission
lines to connect the new Chandranigahpur Substation and 33/11 kV distribution
substations at Harsha, Haripur, Gaur and Nijgadh. These reinforcement will
reduce the losses and improve the reliability and quality of supply in the area.
The Project is estimated to cost US$ 6 million and is funded jointly by GoN, NEA
and IDA. About 50% of works of Chandranigahpur Substation has already been
completed. Equipment required for the substation are scheduled to reach site by
the end of 2007. Contract for Supply and construction of 33 kV sub-transmission
line will be awarded shortly. The Project is scheduled to be completed by 2008.
Grid Substations Reinforcement Project:
Grid Substations Reinforcement Project envisages to reinforce the existing Grid
substations with a view to maintain the reliability of the supply by matching
the Grid substations capacity with the growing demand. The Project comprises of
the following components:
(a) Installation of one unit of 132/33 kV, 30 MVA, 3-phase power transformer
along with associated control and protection panel in Anarmani Substation in
Mechi zone.
(b) Installation of one unit of 132/11 kV, 30 MVA, 3-phase power transformer and
associated bay extension in Pokhara Substation.
(c) Installation of 132/66 kV, 3x12.6 MVA power transformer (bank of three
single-phase transformers) along with associated control and protection panel at
Siuchatar Substation in Kathmandu.
Construction works in above three substations are under progress. The Project is
estimated to cost US$ 3.24 million and is jointly funded by GoN, NEA, ADB and
OPEC. The Project is scheduled to be completed by the end of 2007.
Kawasoti 132
kV Substation Project
Kawasoti 132 kV Substation Project is being undertaken to meet the growing
electricity demand in the eastern part of Nawalparasi District. This Project
will provide the infrastructure for the expansion of 33/11 kV
sub-transmission/distribution network to cover a large number of rural hilly
area in the northern part of the district.
Under this Project, the existing Bardghat-Bharatpur 132 kV transmission line
will be looped-in-out at Pragatinagarto form a new 132/33/11 kV substation. The
existing Bharatpur—Kawasoti 33 kV line will be isolated from Bharatpur
Substation and fed from the new substation. Major components of the Project
consist of two 132 kV line bays, one 132 kV transformer bay with a 132/33 kV, 30
MVA power transformer, another 33 kV transformer bay with a 33/11 kV, 8 MVA
power transformer and 11 kV cubicles.
The project is jointly funded by the GoN, NEA and the Government of Japan (G0J).
The Project is estimated to cost NRs.61 5 million part of which will be met by
the Japanese grant of JP 847 million. EIA study and land acquisition works have
been completed. Consultant has been appointed and detail design work of control
building and substation is under progress. The Project is scheduled for
completion in FY 2008/09.
Grid Operation Department
Grid Operation Department is responsible for the operation and maintenance of
transmission system of Integrated Nepal Power System (INPS). In addition to the
operation and maintenance of transmission system, it has also the responsibility
of upgrading, reinforcing and rehabilitation of transmission system. Major
activities of this Department are described below.
Transformer Upgrading, Reinforcement and Voltage Improvement Works
The overloaded
10 MVA, 132/33kV Transformer at Lahan Substation was replaced with 20 MVA
Transformer. A 6.3 MVA, 66/11kV Power Transformer has been added at Simara
Substation. Reactive compensation measures was implemented atAnarmani Substation
by installing a 2x7.5 MVAR, 33 kV capacitor bank to resolve the severe low
voltage problem at eastern Nepal.
Other Reinforcement Works
Existing 16 sets of 11kV Minimum Oil Circuit Breakers (MOCB) were replaced with
Vacuum Circuit Breakers (VCB) at Balaju Substation. The damaged 6 MVA, 66/11 kV
Power Transformer at Siuchatar Substation was repaired and put into operation.
Following major works are under progress:
Installation and construction of 6.3 MVA,66/11 kVtransformerand bay at Sunkoshi
Power Station and 15 MVA, 132/33 kV transformer and bay at Lamosanghu Substation
for evacuating the power from IPPs projects in Sunkoshi corridor; Installation
and construction of bay for 10 MVA, 132/33 kV power transformer and bay, 3 MVA,
33/11 kV transformer and bay at Damauli Substation; Shifting and installation of
8/10 MVA, 132/33 kV power transformer from Lahan Substation to Kohalpur
Substation; Installation of 45 MVA, 132/66 kV power transformer and bay at
Parwanipur Substation; Construction of 132 kV double busbar system at Butwal and
Chanauta Substations; Upgradation of protection system at Lahan Substation;-
Replacement of 8 MVA, 33/11 kV transformer by new 16.6 MVA transformer and
replacement of old circuit breakers with new VCB at Butwal Substation.
Testing and Maintenance works
Altogether 853 numbers of relays and 226 numbers of energy meters were tested in
various Grid substations including energy meters of IPP and NEA owned Power
Stations. Routine maintenance works were carried out as per schedule in
different substations and transmission lines.
System Operation Department
Load Dispatch Centre (LDC) under System Operation Department provides the real
time supervision and control of the Integrated Nepal Power System (INPS) using
state of art Supervisory Control and Data Acquisition (SCADA) system. FY 2006/07
was a challenging year for system operation. The gap between the supply and
demand both in terms of capacity and energy was so huge that NEA had no option
but to enforce system wide Load shedding. However, diligent efforts were made to
minimise load shedding to the extent possible.
Performance-wise, total number of system trippings was reduced to 19 from 21 in
FY 2005/06, 24 in FY 2004/05 and 28 in FY 2003/04. The availability of real time
data and better communication system have improved the overall availability of
power stations and transmission lines and has helped to minimize the time
required for restoration of the power system in case of black-outs. This has
contributed in the reduction of financial losses of
NEA.
For the efficient operation of IN PS, it is necessary to obtain real time data
from the power stations and substations. The trained manpower of LDC completed
the computerization in the substations using in-house capability. Several fibers
optic lines have been leased to Nepal Telecom and other private companies
thereby generating additional revenue for NEA. System Operation Department also
launched the yearly system operation report A Year in Retrospect 2062/063 in
presence of Honorable Minister of State for Water Reassures and other
dignitaries.