ENVIRONMENTAL AND SOCIALMANAGEMENT PLAN OF GRID TIED SOLAR POWER PROJECT, BLOCK NO. 2, NUWAKOT (8.3MW)

Updated Date : 2018-04-16
The project site Block No 2; Staff Quarter and Forebay area of Devighat powerhouse (PH), is selected for installation of PV solar farmhouse with a capacity of 8.3MW.The project site is located at Devighat Colony area of Bidur Municipality-6(the then Charghare VDC) of Nuwakot district. The name of the settlement around the project area is Mandredhunga settlement.The project site consists of two areas i.e. Forebay area (6.28ha) and Staff Quarter area (6.24ha). The total area required for this subproject is 12.52ha land which is already owned by NEAduring r the construction of Devighat Hydro power project in FY 2036/37 (1984 AD).