Engineering Services Business Group
Engineering Services Business
Group provides technical support on all aspects of hydropower development
ranging from project identification studies to detailed design and construction
supervision of hydroelectric projects. It has two decades of experience in
design and construction supervision of hydroelectric projects with capacities up
to 144 MW. The business group is headed by the General Manager. The four
departments, under this business group are Project Development Department,
Environment and Social Studies Department, NEA Training Center and Soil, Rock
and Concrete Laboratory. The field of services offered by this business group
also includes ElectroMechanical design, operation and maintenance of two
concrete pole plants and a central workshop. Activities carried out by the
business group during FY 2006/07 are as follows:
Project Development Department
Upper
Trishuli -3A Hydroelectric Project
NEA has recently completed Detailed Project Report of Upper Trishuli—3A
Hydroelectric Project with installed capacity of 60 MW. The Project is located
in Rasuwa and Nuwakot districts. The headworks lies nearly 15 km north of the
existing Trishuli Hydropower Station diversion weir and the powerhouse is at
Simle which is about 5 km south of the proposed headworks.
Only 2 km of new road will have to be built along with the upgrading of 14 km of
road between Betrawati and headworks site. NEA has carried out detailed
hydrological studies at the site. The river is characterized by high firm flow
as much of the discharge is fed from snow. NEA has also carried out 353 m of
drilling and 3 km of seismic survey as part of the geological investigation.
The headworks comprises of a 10 m high diversion weir with 4 radial gates. It
will also have a fish passage cum downstream release channel. The waterways
comprises of intake channel, twin desander, 4.1 km long headrace tunnel with a
diameter of 5.4 m, inclined shaft, pressure tunnel and ancillary structures. The
headrace tunnel passes through quartzite and phyllite.
The underground powerhouse will have two units of Turbine generators. Power
evacuation will be made through a 54 km long 220 kV transmission line connecting
the Project to Matatirtha substation in Kathmandu. Annual energy generation is
estimated to be 488 GWh.
Estimated cost of the Project is US$ 109 million and the Project economics study
shows an EIRR of 20%. The Project is to be commissioned by 2011 if preparatory
works are carried out accordingly. NEA is currently undertaking Environmental
Impact Study of the Project. This Project is to be built by GoN and NEA through
soft loan from Government of China.
Upper
Trishuli-3B Hydroelectric Project
Upper Trishuli -3B Hydroelectric Project is the tailrace scheme of Upper
Trishuli-3A. This Project will have an installed capacity of 44 MW. NEA is
currently conducting feasibility study with the aim of completing the Project by
FY 2011/12. This Project comprises of a 3.1 km long headrace tunnel, inclined
shaft, surface powerhouse with two units and ancillary structures. Power
evacuation will be made through the proposed 220 KV line of Upper Trishuli -3A.
Topograhic survey and geological investigation have been carried out and layout
of the structure have been accomplished. This study will be completed in the FY
2007/08. Since separate headwork and transmission line is not required, this
Project can be built in a much economical manner.
Upper Seti (Damauli) Storage Project
NEA has completed Upgrading Feasibility Study of Upper Seti (Damauli) Storage
Project under the technical assistance from Japanese Government through JICA. It
has an installed capacity of 128 MW and will be able to generate 476 GWh of
annual energy. This scheme, upon completion, will be able to provide six hours
of daily peaking capacity in winter which is much valuable to the present power
system. The Project will comprise of a 140 m high concrete dam, 195m long
penstock, underground powerhouse and ancillary structures. Power evacuation will
be made through 40 km long 220 kV line connecting the Project to the new
Bharatpur substation. Estimated cost of the Project is US$ 328 million. The
Project has a construction period of six years and can be commissioned by
FY2014/15. Project Identification Study
In FY 2006/07, project identification studies of two projects namely Tamakoshi-V
and Tila-3 were carried out.
Tamakoshi —V Hydroelectric Project with a capacity of 28 MW is located in
Dolakha District approximately 170 km north-east of Kathmandu. The road
connecting Singati Bazaar and Lamabagar which is being built for Upper Tamakoshi
Hydropower Project (UTKHEP) passes through both powerhouse and headworks sites
of Tamakoshi-V Project. This Project is conceptualized as a cascade project with
UTKHEP. The headrace tunnel has a length of 2.5 km. Estimated annual generation
is 158.80 GWh per year. Power evacuation from this scheme will be made through
6.0 km long 220 kV Transmission Line connected with the nearest substation at
Gongar. Total project cost is estimated at US$ 45 million.
Tila-3 Hydroelectric Project is located in Kalikot District, Karnali Zone
approximately 190 km North of Surkhet. It is a high head run of river project
with a capacity of 116 MW. Karnali highway passes along the powerhouse and the
headwork area of this Project. The headrace tunnel will be about 7.25 km long.
Annual generation is estimated to be 680.20 GWh. A 144 Km long 132 kV double
circuit transmission line is required to evacuate power to Kohalpur substation.
Total project cost is estimated at US$ 204 million.
Other Activities
Engineering Services Business Group is also involved in providing technical
support to various projects. The commercial activities carried out by
Engineering Services include construction design and supervision of Chamelia HEP
and detailed design of Kulekhani Ill HEP etc. This business group has also
carried out detailed survey of Duhabi
—Jogbani and Butwal-Sunauli 400 kV Transmission Line. It has also completed
detail survey of Kabeli Corridor 132 kVTransmission Line in FY2006/07.
In FY 2006/07, study on Kulekhani reservoir sedimentation and study on slope
stabilization work of Puwa Khola HEP were also carried out. Project Development
Department also operates two concrete pole plants at Kotre and Amlekhgunj. These
pole manufacturing plants have greatly helped in supplying the materials
required for various rural electrification projects. It also runs central
workshop at Hetauda where transformer repair works are carried out.
Upper Tamakoshi Hydroelectric Project
(UTKHEP)
The detailed design of Upper Tamakoshi HEP with an installed capacity of 309 MW
is being carried out in FY 2006/07. This is a peaking run-of-river type project
with an annual average energy of 1,737.7 GWh. The gross head and design
discharge of this Project are 820 m and 44 m3/s respectively.
Major structures of this Project comprise of a concrete dam of height 22.5 m,
intake, twin desanding basins, headrace tunnel of length 7.2 km, 2.5 km long
pressure shaft, underground powerhouse, 2.5 km long tailrace tunnel and 47 km
long 220 kV Transmission Line.
Based on the present generating capacity and peak demand, it is estimated that
in 2013 the power deficit will be 483 MW. Therefore, NEA has placed high
priority to start the construction of the project by the end of 2008 so as to
complete it by FY 2012/13. The Project cost is estimated at US$ 340 millions
(excluding IDC and other financial costs). Its levelised unit cost is US Cent
2.6/kWh and benefit-cost ratio is 2.2. The Project will have a construction
period of 4.5 years.Detailed engineering design and preparation of tender
documents has been commenced from February 2007 by Norconsult-Lahmeyer
International JN. The detailed design works is scheduled to be complete by
November 2008. Out of 61.5 km access road, 33 km fair-weathered road from
Dolakha to Singati is in operation whereas the remaining 28.5 km up to Lamabagar
is under construction. Construction of three steel truss bridges along the
access road will be commenced soon. Environmental Impact Assessment (E IA)
report for generation has been approved by Ministry of Environment, Science and
Technology (M0EST) while EIA Report for Transmission Line is under final stage
of the approval. Construction of a test adit of 500 m length has been started
under the Detailed Design Program. Land acquisition for 28.5 km access road is
nearly completed. Two office buildings have been constructed, one each in
headworks and powerhouse sites. Communication facilities have also been
established in both places. In order to implement the Project by mobilizing
funding from within the country, NEA is negotiating with Karmachari Sanchaya
Kosh and other domestic financial institutions.
Soil, Rock and Concrete Laboratory
Soil, Rock and Concrete Laboratory has been providing quality services relating
to material testing, geological and geotechnical engineering fields for
hydroelectric project study.
Geological mapping, geophysical survey and core drilling are the major
activities carried out by this Department. It also provides services like
construction material investigation, both in-site and laboratory testing. The
state of art laboratory provides services on a regular basis to NEAand other
clients. The Department also carries out geotechnical design including rock
support pattern for underground and surface structures.
The followings works were undertaken by the laboratory in FY 2006/07. Surface
geological mapping, core drilling, geophysical survey and construction materials
investigation carried out for Upper Trishuli-3B Hydrelectric Project. Additional
core drilling at downstream weir option of Upper Trishuli — 3A HEP. Core
drilling at option-3B powerhouse of Upper Seti (Damauli) Storage HEP. Core
drilling at Middle Bhote Koshi HEP. Drilling was carried out in Sunkoshi River
at three alternative dam sites of Sun Koshi Storage-Cum-Diversion Scheme in
Okhaldhunga District. Topographical survey work at Upper Tamakoshi HEP. Sediment
Analysis of Upper Seti (Damauli) Storage HEP
Concrete quality test at Bhiman Sub-station of Sindhuli. Concrete Mix Design and
various tests on rock, soil and concrete for different private party.
Environmental And Social Studies Department
Environmental and Social Studies Department provide services related to all
aspects of environmental studies of projects in the planning, construction and
operational phase. NEA has been carrying out Environmental studies since 1987.
The Environmental Unit of those days has evolved into ESSD with a wealth of
experience in conducting Environmental Impact Assessment (EIA), Initial
Environmental Examination (lEE), Strategic Impact Assessment (S IA) and
Acquisition Compensation Rehabilitation Program (ACRP). This Department also
conducts environmental monitoring and auditing of hydroelectric, transmission
line and distribution line projects.
The Department accomplished the following assignments during the fiscal year
2006/07:
(a) The EIA report of Upper Tamakoshi Hydroelectric Project has been approved.
(b) The EIA report of Kawasati 132/33 kV Substation Project has already been
approved.
(c) The lEE of Chandranighapur 33 kV Transmission Line Network has been
approved.
(d) The updated EIA of Hetauda-Bardaghat 220 kV Transmission Line is in the
final stage of approval.
(e) The Department is conducting quarterly monitoring of air, noise and water
quality of Middle Marsyandhi Hydroelectric Project under construction.
(f) The EIA of Upper Trishuli-3A Hydroelectric Project (UT-3A) is being carried
out.
(g) The Scoping Document and Terms of Reference of Upper Trishuli-3B
Hydroelectric Project (UT-3B) is in the process of approval.
(h) The Department is in the process of awarding the EIA study of Cross-Border
Butwal-Sunauli and Duhabi-Jogbani 400 kV Transmission Line to the local
consultant under its supervision.
(i) The Scoping Document and Terms of Reference of Damauli-Bharatpur 220 kV
Transmission Line is in the process of approval.
(j) The lEE of Dolakha-Nayapul 33 kV Transmission Line and EIA report of Gongor
Khimti 220 kV Transmission Line is in the process of approval.
NEA Training
Center
NEA Training Center (NEA-TC) has been providing need-based short term
trainings to NEA employees with an aim to upgrade their professional knowledge
and skills at operational and managerial levels. The training programs are
designed as per training needs assessment (TNA) at organization and personnel
level after discussion with the corporate executives and general managers level.
Since the last two years, NEA-TC has expanded its services to include the
clients outside of NEA. It has conducted various training programs to clients on
their request which include Department of Electricity Development, Chilime
Hydropower Co., Butwal Power Co. Ltd. and consumer community. For the first
time, NEA-TC has conducted training program for foreign participants. In
FY2006/07, five persons from Afganistan took part in powerhouse operation and
maintenance training at Panauti Powerhouse. On the request of Small Hydropower
Promotion Project of GTZ, training was imparted to the consumer community of
Goplingtar lift irrigation scheme. A total of 692 staff were trained in FY
2006/07 which included 270 officers and 422 non officers. A total of 61 training
programs were conducted in this period.